Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 95 Framework agreements
Chapter 8 – Purchasing techniques
(1) A framework agreement shall be concluded following one of the procedures in this Act, cf. section 55.
(2) A framework agreement may have a term of no more than 4 years. In exceptional cases, a framework agreement may be concluded for a longer period.
(3) Contracts based on a framework agreement shall be concluded during the term of the framework agreement. The contracts may apply for a period after the expiry of the term of the framework agreement.
Cross-references
This section refers to
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 95. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 24/10576Not upheld
Takeda Pharma A/S v Amgros I/S
The complaint concerned a framework agreement for collecting plasma from the Danish blood centres and supplying plasma-derived medicines, and challenged a sub-criterion on immunoglobulin yield, the incumbent's competitive advantage and a duration of more than four years. The Complaints Board found that the sub-criterion was linked to the subject-matter of the contract and sufficiently clear, that Amgros had sufficiently neutralised the incumbent's advantage, and that security of supply justified a duration beyond four years under section 95(2).
Provisions applied: section 2, section 95(2), section 159(3), section 160(1), section 163(1)Read the decision (Danish)
On this site
Previous section
Section 94 — Setting of time limits and opening of tenders
Next section
Section 96 — Framework agreements
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.