What is a framework agreement?

An agreement between one or more contracting authorities and one or more economic operators which sets the terms governing contracts to be awarded during a given period, in particular as regards price and the quantities envisaged (section 24(xxx) of the Public Procurement Act). See the guide on framework agreements.

Legal basissection 24(xxx) · official text

How long may a framework agreement run?

At most 4 years. In exceptional cases it may be concluded for a longer period (section 95(2) of the Public Procurement Act). Contracts must be concluded during its term, but they may remain in force after it expires (section 95(3) of the Public Procurement Act).

Legal basissection 95(2) · section 95(3) · official text

Who may use a framework agreement?

The contracting authorities named in the contract notice (section 96 of the Public Procurement Act).

Legal basissection 96 · official text

How are contracts awarded when the framework has several suppliers?

By direct award or by reopening competition, and both may be used under the same framework (section 98(1) of the Public Procurement Act, section 98(2) of the Public Procurement Act). The choice must be made on objective criteria laid down in the procurement documents (section 98(2) of the Public Procurement Act).

Legal basissection 98(1) · section 98(2) · official text

What is the difference between direct award and reopening of competition?

Direct award is made on the basis of the terms of the framework and the objective criteria in the procurement documents (section 99 of the Public Procurement Act). When competition is reopened, the capable suppliers are invited simultaneously and in writing to tender on the same terms or on terms formulated more precisely (section 100(1) of the Public Procurement Act, section 100(2) of the Public Procurement Act).

Legal basissection 99 · section 100(1) · section 100(2) · official text

Does the standstill period apply to contracts under a framework agreement?

No, the standstill period does not apply where a contract is awarded under a framework agreement, with or without reopening of competition (section 3(3)(ii) of the Complaints Board Act).

Must a notice be published when a framework agreement is concluded?

Yes, a contract award notice must be sent to the EU Publications Office no later than 30 days after the contract or framework agreement is concluded (section 129(1) of the Public Procurement Act).

Legal basissection 129(1) · official text

What is the difference between a framework agreement and a dynamic purchasing system?

A dynamic purchasing system must be open at all times to candidates that meet the minimum requirements (section 104(3) of the Public Procurement Act). A framework agreement has a fixed set of parties and, as a rule, a term of at most 4 years. See the guide on dynamic purchasing systems and auctions.

Legal basissection 104(3) · official text