Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 151 European Single Procurement Document
Chapter 12 – Evidence concerning exclusion, minimum requirements of suitability and selection
(1) Before the contracting authority's decision on the award of the contract, a contracting authority shall require the tenderer to which the contracting authority intends to award the contract to submit evidence under section 152 of the information provided in the European Single Procurement Document under section 148, cf. however subsections (3) and (5). The contracting authority shall set an appropriate time limit for the tenderer to submit the evidence.
(2) The contracting authority may, at any point during the procurement procedure, require the candidate or tenderer to submit evidence as referred to in section 152, cf. however subsections (3) and (5), where this is necessary to ensure the proper conduct of the procedure. In such situations, the contracting authority shall set an appropriate time limit for the candidate or tenderer to submit the evidence.
(3) Subsection (1) does not apply to contracts based on framework agreements where such contracts are awarded in accordance with section 97 or section 98(1)(i).
(4) The contracting authority may request the candidate or tenderer to supplement or clarify evidence received pursuant to sections 153-155, 157 and 158.
(5) Notwithstanding subsections (1) and (2), the candidate or tenderer is not obliged to submit the evidence where
(i) the contracting authority can obtain the certificates or the relevant information directly by accessing a national database, or
(ii) the contracting authority already holds the necessary evidence from previously conducted procurement procedures.
Cross-references
This section refers to
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 151. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 22/14568Partly upheld
Scania Danmark A/S v I/S REFA
Scania challenged REFA's award of a contract for the supply and servicing of refuse collection vehicles to Hessel. The Complaints Board found that REFA had not verified before the award that Hessel met the minimum requirement of suitability of four references, contrary to section 159(2), and that Hessel's tender contained a reservation against the minimum requirement for LED lighting, so it should not have been considered under the principles in section 2; the award decision was annulled, while a claim about the number of vehicles stated in the tender failed.
Provisions applied: section 2, section 151(1), section 152(1), section 155(ii), section 159(2), section 159(3)Read the decision (Danish)Case 23/03361 og 23/03362Partly upheld
Meldgaard Miljø A/S v Afatek A/S
The complaint concerned Afatek's repeated use of the accelerated procedure with a 15-day time limit for receipt of tenders in two open procedures for the disposal of incineration slag, citing limited storage space. The Complaints Board found that the accelerated procedure had been used without justification under section 57(5), that shortening the time limit to 15 days without reasons and the short time limit for evidence of the ESPD information breached section 2, and that the contract notice, contrary to section 2, section 128(2) and section 140(2), did not describe the grounds for exclusion and the suitability criteria; the claim for annulment was not upheld.
Provisions applied: section 2, section 57(1), section 57(2), section 57(4), section 57(5), section 128(2), section 140(2), section 151(1)Read the decision (Danish)
On this site
Previous section
Section 150 — European Single Procurement Document
Next section
Section 152 — Evidence
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.