The Public Procurement Act (udbudsloven) sets minimum time limits that give candidates and tenderers time to apply and to tender. The contracting authority must fix an adequate time limit, which is at least the minimum for the chosen procedure (section 93(1) of the Public Procurement Act). This guide covers the minimum periods, reduction and extension, additional information, and the periods that run after the award. Use the deadline calculator to find the actual date.

How the periods are counted

Where the Act sets a time limit in days, it generally runs from the day after dispatch: of the contract notice, or of the invitation to tender (section 57(2) of the Public Procurement Act, section 60(2) of the Public Procurement Act). The day of dispatch itself is not counted. The starting point for the contract notice is the dispatch to the Publications Office of the EU, not the later publication. The standstill period is counted in calendar days from the day after the notice of the award decision is sent (section 3(1)(i) of the Complaints Board Act).

Minimum time limits by procedure

ProcedureTime limitCounted from
Open procedure, tenders35 days (section 57(2) of the Public Procurement Act)day after dispatch of the notice
Restricted procedure, requests to participate30 days (section 59(2) of the Public Procurement Act)day after dispatch of the notice
Restricted procedure, tenders30 days (section 60(2) of the Public Procurement Act)day after dispatch of the invitation
Negotiated procedure, requests to participate30 days (section 63(2) of the Public Procurement Act)day after dispatch of the notice
Negotiated procedure, initial tenders30 days (section 65(2) of the Public Procurement Act)day after dispatch of the invitation
Competitive dialogue, requests to participate30 days (section 68(5) of the Public Procurement Act)day after dispatch of the notice
Innovation partnership, requests to participate30 days (section 74(5) of the Public Procurement Act)day after dispatch of the notice
Innovation partnership, initial tenders30 days (section 76(2) of the Public Procurement Act)day after dispatch of the invitation

For final tenders in competitive dialogue, in the negotiated procedure and in the innovation partnership, the authority must fix an adequate time limit (section 71(2) of the Public Procurement Act, section 66(6) of the Public Procurement Act, section 77(7) of the Public Procurement Act), but the Act gives no minimum number of days. In the negotiated procedure without prior publication there is no notice and therefore no minimum time limit.

Shortening the time limits

The Act provides three possibilities, which can to a large extent be combined with the rules for each procedure:

In the restricted procedure and the negotiated procedure, non-central government authorities may also agree the time limit for tenders with the selected candidates, provided all have the same time. It may not be less than 10 days from the day after the invitation is sent (section 60(5) of the Public Procurement Act). The same possibility exists in the innovation partnership (section 76(2) of the Public Procurement Act).

Extending the time limit

The authority may extend the time limit for requests to participate or tenders. It must extend it if (section 93(4) of the Public Procurement Act):

  1. additional information or documents are provided later than 6 days before the time limit (section 93(4)(i) of the Public Procurement Act),
  2. the procurement documents are materially changed (section 93(4)(ii) of the Public Procurement Act),
  3. documents not made freely available by electronic means are not sent within 5 days of a request (section 93(4)(iii) of the Public Procurement Act), or
  4. the time limit was shortened for urgency and the information is provided later than 4 days before it (section 93(4)(iv) of the Public Procurement Act).

If tendering requires a site visit or inspection of documents at the authority, the time limit must be longer than the minimum so that tenderers can obtain the necessary information (section 93(2) of the Public Procurement Act).

Additional information and changes

The authority must provide additional information and documents no later than 6 days before the time limit expires (section 134(2) of the Public Procurement Act); where the time limit was shortened for urgency, 4 days (section 134(3) of the Public Procurement Act). Changes to the procurement documents must be published appropriately, notified within the same periods, and may not change fundamental elements (section 134(1) of the Public Procurement Act). The authority may examine applications and tenders only after the time limit has expired (section 94 of the Public Procurement Act).

After the award: standstill and notice

Once the authority has decided to award a contract, all affected candidates and tenderers must be notified, and the notification must state when the standstill period expires (section 171(4) of the Public Procurement Act). The contract may be concluded no earlier than the end of the standstill period (section 173 of the Public Procurement Act). The period is 10 calendar days from the day after dispatch if the notification was sent electronically, and 15 calendar days if sent by letter (section 3(1) of the Complaints Board Act). The authority may set a longer period (section 3(2) of the Complaints Board Act). The standstill period does not apply in the cases in section 3(3) of the Complaints Board Act, for example procurement without prior publication of a contract notice or an award under a framework agreement. A contract award notice must be sent to the Publications Office no later than 30 days after the contract is concluded (section 129(1) of the Public Procurement Act). See award and standstill.

What to watch for

  • Build in a buffer where the procurement documents are complex, even if the minimum is met. The time limit must be adequate, not merely lawful (section 93(1) of the Public Procurement Act).
  • Answer questions early. A late answer may force you to postpone the time limit.
  • Record the dispatch date, as it determines when the periods run.