Consolidated Act No. 116 of 3 February 2025 · Part II · Public procurement above the threshold
Section 93 Setting of time limits and opening of tenders
Chapter 7 – Procurement procedures and design contests
(1) A contracting authority shall fix adequate time limits for the submission of requests to participate and tenders. The time limit for receipt of tenders and requests to participate shall, as a minimum, comply with the minimum time limit for the procurement procedure concerned.
(2) Where tenders can be submitted only after a visit to the site or after on-the-spot inspection of the documents supporting the procurement documents at the premises of the contracting authority, the contracting authority shall fix a time limit for receipt of tenders such that all tenderers may be aware of all the information needed to prepare a tender. The time limit shall be longer than the minimum time limit indicated for the procurement procedure concerned.
(3) In open procedures, the contracting authority shall state the time limit for receipt of tenders in the contract notice. In restricted procedures, competitive procedures with negotiation, competitive dialogues and innovation partnerships, the contracting authority shall state the time limit for receipt of requests to participate in the contract notice, and the time limit for receipt of tenders shall appear from the procurement documents.
(4) A contracting authority may extend the time limit for receipt of requests to participate or tenders. The contracting authority is obliged to extend the time limit for receipt of requests to participate or tenders in the following cases:
(i) Where the contracting authority provides additional information concerning the procurement documents or additional documents later than 6 days before the time limit fixed for receipt of requests to participate or tenders.
(ii) Where the contracting authority makes substantial changes to the procurement documents.
(iii) Where the contracting authority does not, within 5 days of a request to that effect, send the documents to which free, direct and full electronic access has not been offered, cf. section 132(2).
(iv) Where the contracting authority has shortened the time limit because of an urgency on the part of the contracting authority, cf. section 57(5), section 59(3) and section 65(2), cf. section 60(6), and the contracting authority provides additional information concerning the procurement documents or additional documents later than 4 days before the time limit fixed for receipt of requests to participate or tenders.
Cross-references
This section refers to
Referred to by
Decisions of the Complaints Board
Decisions in which the Complaints Board for Public Procurement applied section 93. The summaries are Procurelex’s own; the full decision, in Danish, is on the Board’s portal.
Case 23/07108Not upheld
Oshkosh Airport Products, United States of America v Forsvarsministeriets Materiel- og Indkøbsstyrelse
Oshkosh Airport Products, which did not submit a tender, challenged several technical specifications in Forsvarsministeriets Materiel- og Indkøbsstyrelse's open procedure for crash tenders for military airports, including requirements on width, height, engine and brakes, as well as the time limit for receipt of tenders. The Complaints Board found that the requirements were objectively justified by the contracting authority's needs within its wide discretion under section 40(4) and section 2, and that the time limit complied with the minimum time limit in section 57.
Provisions applied: section 2, section 40(4), section 42, section 57(2), section 57(4), section 93Read the decision (Danish)Case 22/14577Partly upheld
Dustin A/S v Staten og Kommunernes Indkøbsservice A/S
Dustin challenged several aspects of SKI's procurement of a framework agreement for computers, including an extension of the time limit, modifications of the procurement documents, references to specific makes and the award to Comm2IG. The Complaints Board found that SKI breached section 2 by sending the notice extending the time limit to the EU Publications Office only after the time limit had expired and, by a majority, by awarding both lots to Comm2IG without the check described in the tender conditions although its tenders were non-compliant, and annulled the award decision, while the claims concerning modifications of the procurement documents (sections 93 and 134) and section 42 were rejected.
Provisions applied: section 2, section 24(xxxvii), section 42(2), section 93(3), section 93(4)(ii), section 134(1), section 134(2)Read the decision (Danish)Case 21/10894Partly upheld
Atea A/S v Region Sjælland
The complaint concerned a framework agreement for an indoor mobile coverage system (DAS) for Region Sjælland's hospitals, where the drawings provided were not accurate. The Complaints Board held that the region breached section 2(1) by not neutralising the incumbent's competitive advantage as far as possible and by not publishing an extension of the time limit as a corrigendum to the contract notice, but rejected the claims on a change of fundamental elements and an insufficient extension of the time limit under section 93(4); it annulled the award decision.
Provisions applied: section 2(1), section 24(xxxvii), section 93(3), section 93(4)(i), section 93(4)(ii), section 185(2)Read the decision (Danish)
On this site
Previous section
Section 92 — The jury
Next section
Section 94 — Setting of time limits and opening of tenders
Want your tender documents checked before publication? We will show you how Procurelex Kontrol does it.
Request a demoGeneral information on the Public Procurement Act in force. Not legal advice.